Development consent in NSW is the formal approval, granted under Part 4 of the Environmental Planning and Assessment Act 1979, to carry out a particular development on a particular piece of land. You apply for it by lodging a development application (DA), usually with your local council. Not every project needs one: minor work can be exempt, and straightforward work can go through a fast-track complying development certificate (CDC). This guide explains which path applies, how the DA process runs, and what buyers, sellers, builders and developers should check along the way.
TL;DR
- Development consent is the approval of a DA. The consent authority is usually the local council.
- Minor work may be exempt, and low-impact work may qualify for a CDC. Everything else generally needs a DA.
- The DA process runs through pre-lodgement, lodgement, assessment, determination and post-decision stages. The outcome is consent with conditions, refusal, or deferred-commencement consent.
- Consent generally lapses after five years unless work has physically commenced. Consent alone does not let you build: you also need a construction certificate.
- If you are buying, check the property’s consent history and zoning before you exchange contracts.
Table of Contents
- What development consent actually is
- Do you need development consent?
- The DA process, step by step
- Who decides, and how neighbours have their say
- The three possible outcomes
- Consent is not the last approval
- How long does development consent last?
- Buying a property: check the consent before you sign
- Selling with approvals in order
- Builders and developers: planning the legal side
- How we can help
- FAQ
What development consent actually is
The NSW Government’s DA glossary defines development consent as consent under Part 4 of the Act to carry out development. A DA is the application you make to get it. Think of the DA as the request and the consent as the answer, if the answer is yes.
A CDC sits slightly apart from a DA, but the glossary says a CDC is generally included in the statutory meaning of development consent unless a provision expressly excludes it. That matters when you read a contract for sale or a planning document and see the term used loosely.
Development, in planning terms, is wider than building. It covers using land for a new purpose, changing the use of existing premises, subdividing, and carrying out building work. The NSW Government explains that the system exists to manage cumulative environmental impacts, balance public and private interests, let the community have input, and make sure matters such as infrastructure, safety, sunlight and ventilation are addressed.
Do you need development consent?
There are three broad pathways, as set out in the NSW Government’s planning approval pathways guidance.
| Pathway | What it covers | Who approves it |
|---|---|---|
| Exempt development | Minor, low-impact work that meets the standards in the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 | No planning or construction approval needed |
| Complying development (CDC) | Straightforward residential, commercial and industrial work that meets set standards and land requirements | Council or an accredited private certifier |
| Development application (DA) | Development that needs consent and is not exempt or complying | Usually the local council |
Exempt development
The NSW Planning Portal says exempt development needs no planning or construction approval, but only where both the work and the site satisfy the applicable standards. Its examples include decks, garden sheds, carports, fences, window repairs and house painting. “Exempt” is not a blanket permission. A shed that is too large, too close to a boundary or on a heritage or bushfire-affected lot may fail the standards and need approval after all.
Complying development
Complying development is the fast track. The NSW Planning Portal says it can include a new one- or two-storey home, a granny flat, structural earthworks, a swimming pool, demolition, a home-based enterprise, some renovations, strata subdivision and fire-safety works. Your project must meet the specified standards, and the land must be eligible. If it does, a council or private certifier can issue the approval without a full DA.
Everything else: local development
The Planning Portal explains that local development needs consent when an applicable local environmental plan (LEP) or SEPP requires it, and the proposal is neither regionally significant nor state significant development. Larger or more sensitive proposals are decided by other bodies, which we cover below.
To find out where your project sits, check the zoning tables in the relevant LEP and SEPP. The NSW Spatial Viewer shows a property’s zoning and planning constraints by address. Each use is either permitted without consent, permitted with consent, or prohibited. A prohibited use cannot be approved however well the DA is prepared.
If you are a developer or builder weighing up a site, this zoning check is the first thing to do, before you commit to a contract. Our Rapid Planning Consultation, from $1000, is designed for that early stage, and our page on subdivisions and property development in NSW covers the legal side of splitting or developing land.
The DA process, step by step
The NSW Department of Planning’s assessment guide presents five stages: pre-lodgement, lodgement, assessment, determination and post-decision. Here is what each means in practice.
1. Pre-lodgement: check and prepare
Before you lodge, check the relevant LEP and SEPP, then prepare your application. The Planning Portal lists the core documents: a description of the development, its estimated cost, a plan of the land, a sketch of the proposed development and an environmental assessment. Many councils offer pre-lodgement meetings, which are worth taking up on anything beyond a simple project. Problems found here cost little to fix. The same problems found after lodgement cost time.
2. Lodgement
You lodge the application with the local council, which in NSW is generally done through the NSW Planning Portal. At lodgement, the council checks the application for completeness, identifies issues through a clearing-house process, works out the assessment stream and allocates the application to an assessment officer.
3. Assessment
The NSW Government’s DA guide says the assessment clock starts when the information provided is adequate, and it can stop while council waits for information it has requested. The applicant is responsible for providing enough detail for a decision. In practice, a thin application is the most common reason a DA drags on.
Councils must weigh matters including the applicable plans and policies, impacts on the natural and built environment, social and economic impacts, whether the site is suitable, submissions from the public, and comments or approvals from relevant agencies.
4. Determination
The decision is made, and one of three outcomes follows (see the next section).
5. Post-decision
You satisfy the conditions, obtain the required certificates, and, if you disagree with the decision, consider a review or appeal.
Who decides, and how neighbours have their say
The Planning Portal says the consent authority is usually the local council, or the Minister for Planning where a SEPP specifies. The DA glossary adds that it may instead be a joint regional planning panel, a local planning panel, a public authority, or another body specified by the Act, regulations or a planning instrument.
For small housing development, the NSW Government says most decisions are made at staff level, for example by an assessment officer, a senior officer, a development assessment manager or director, or the general manager. Bigger or more contested projects tend to go to a panel.
Public notification
Neighbours and the community can comment on many DAs. The Planning Portal says designated development must be publicly notified for at least 28 days, and advertised development must also be notified. Your council’s notification policy sets out how other applications are handled. Submissions are one of the matters the council must consider, so a well-founded objection can shape conditions or the outcome.
If you are applying, talk to your neighbours early. A DA that arrives with no surprises tends to attract fewer objections.
The three possible outcomes
The NSW Government identifies three DA outcomes:
- Consent with conditions. The most common result. You can proceed, subject to the conditions listed.
- Refusal with reasons. The council explains why. You can amend and lodge again, or seek a review or appeal.
- Deferred-commencement consent. The consent does not operate until specified matters are resolved, such as a drainage design or an easement being arranged.
Read the conditions closely
Conditions can modify the approved plans, require compliance with the Building Code of Australia, and require steps such as paying bonds or development contributions. Some must be satisfied before a construction certificate or occupation certificate is issued.
The NSW Government’s guidance indicates conditions are not merely administrative. They can materially change the approved design and the construction cost, so review them with your certifier and builder before you sign a building contract. If the consent involves easements or restrictions on the land, our checklist for easements on title and our guide to Section 88B instruments explain what to look for.
If you disagree with the decision
The NSW Government says a review of determination must be lodged and determined within six months of the decision, and a court appeal must also be lodged within six months. Those windows are firm, so seek advice quickly if you plan to challenge a refusal or a condition.
Consent is not the last approval
A common misunderstanding is that a consent lets you start digging. The NSW Government’s homeowner guide says development consent approves the development proposed in the DA, but building work also needs a construction certificate, issued by council or an accredited certifier, to confirm the work will be safe, healthy and in line with the consent.
After consent, the typical sequence looks like this:
- Satisfy the pre-construction conditions (bonds, contributions, amended plans).
- Obtain the construction certificate.
- Build in line with the plans and conditions.
- Obtain an occupation certificate before using or occupying the building.
- For subdivisions, obtain a subdivision certificate so new lots can be registered.
The Planning Portal groups these as post-consent certificates: subdivision certificates, building information certificates, construction certificates and occupation certificates.
How long does development consent last?
The NSW Government says consent generally lasts five years unless the consent specifies a different period. It lapses if physical commencement has not occurred within that period, and it does not lapse once physical commencement has occurred. Check the wording on your own notice of determination, because a longer or shorter period may apply.
This matters in property deals. A block sold “with DA approval” may have a consent that is close to lapsing. A buyer relying on it could have to start again. Always confirm the date of consent, any stated lapsing period, and whether work has physically commenced.
Buying a property: check the consent before you sign
For buyers and investors, development consent is a due diligence issue as much as a planning one. The Planning Portal recommends using the address-based Spatial Viewer to identify zoning and constraints, then checking the applicable LEP or SEPP to see whether a development is exempt, needs consent or is prohibited.
A practical checklist for a purchase:
- Existing structures. Do the deck, extension, granny flat or pool have consent, or a complying development certificate, and a final occupation certificate where one was needed? Unapproved work can become the new owner’s problem.
- Proposed plans. If the seller says a DA is approved, ask for the notice of determination, the stamped plans and the conditions.
- Lapse date. Confirm the consent has not expired and whether work has begun.
- Zoning. Confirm your intended use is permitted with or without consent.
- Title. Check for easements and restrictions that may conflict with the approved plans.
Our guides to NSW property searches and planning property reports show what each search tells you. Pool owners and buyers should also read our swimming pool compliance checklist. A building and pest inspection can also flag work that looks unapproved.
Buying off the plan? The consent behind the project and the contract’s sunset clause both matter. See what to check before an off-the-plan purchase.
Selling with approvals in order
Sellers benefit from tidying up approvals before listing. If you have built a deck, converted a garage or installed a pool, gather the consent or certificate paperwork and the final occupation certificate. A buyer’s conveyancer will ask for it, and a gap can delay or derail exchange. If something was built without approval, get advice early on whether it can be regularised, since that can affect timing and price.
Builders and developers: planning the legal side
For multi-lot and multi-dwelling projects, consent is only one part of a larger legal sequence: site acquisition, contract conditions tied to approvals, subdivision, easements, Section 88B instruments and the sale of finished lots. We act for builders and developers across NSW on this work, so the contract and the planning timeline line up rather than pulling against each other.
How we can help
We are a conveyancing and property law firm focused only on real estate in NSW. We do not lodge your DA, which is a job for your town planner, architect or certifier. What we do is make sure the legal side of the transaction works with the approvals.
Our published starting prices include a contract review from $250, an urgent contract review from $500, and fixed fee conveyancing from $2500. A purchase with superannuation starts from $4500, and transfers from $2200. A Rapid Planning Consultation is from $1000. If you are buying a property with approvals attached, or a site you plan to develop, talk to us before you exchange so the consent position is checked first.
FAQ
What is the difference between a DA and development consent?
A DA is the application you lodge. Development consent is the approval you receive if the application succeeds. The consent usually comes with conditions you must meet before and during construction.
Do I need development consent for a granny flat or pool?
Not necessarily. The NSW Planning Portal lists both granny flats and swimming pools among the work that can be approved as complying development, which uses a CDC instead of a full DA. This applies only if your lot and design meet the specified standards, so check the zoning and standards for your property first.
How long does a development application take?
The time varies with the project, council and quality of your application. The NSW Government says the assessment clock starts once the information is adequate and can stop while council waits for more. A complete, well-prepared application is the best way to keep the process moving.
Can I buy a property that has development consent?
Yes. Ask for the notice of determination, the approved plans and the conditions, and confirm the consent has not lapsed. Consent generally lasts five years unless physical commencement has occurred. Have your conveyancer review these documents before you exchange contracts.
Can I challenge a council decision?
Yes. The NSW Government says a review of determination, or a court appeal, must be lodged within six months of the decision. Seek advice promptly, as these timeframes are strict.